the complete, computed materials list for this project — concrete first, then the base and steel that make it last. Project pages answer the question calculators can't: 'what do I actually buy?' — every quantity below is computed with the site's own calculator models.
| Slab area | 400 sq ft (37.2 m²) |
|---|---|
| Thickness | 4 in (102 mm) |
| Exact concrete volume | 3.78 m³ (4.94 yd³) |
| Volume incl. 10% extra | 4.15 m³ (5.43 yd³) |
| Pre-mix bags — 80 lb bag | 245 bags |
| Pre-mix bags — 60 lb bag | 326 bags |
| Pre-mix bags — 25 kg bag | 362 bags |
| Pre-mix bags — 20 kg bag | 452 bags |
A 20 × 20 ft slab is the standard two-car garage footprint. At 4 inches thick (the usual spec for cars; go 5–6 in for heavy trucks) the table below is the complete concrete order. Add: a compacted gravel base (about 4 in → 400 sq ft × 0.33 ft ≈ 4.9 yd³), welded mesh or rebar grid, and a vapour barrier sheet of 400+ sq ft.
All quantities computed with the Concrete Calculator's model (manufacturers' bag yields, volume incl. 10% extra), checked 9 November 2026. Prices vary too much by region to quote honestly — take this list to your supplier for local rates.
Concrete Calculator · Brick Calculator · Tile Calculator · Paint Calculator · Roof Pitch Calculator · Deck Calculator
4 inches for cars and sheds; 5–6 inches for heavy vehicles, RVs or where the slab meets the street. Thickness changes every number linearly — the Concrete Calculator adjusts in one step.
On any soil that isn't already compacted rock: yes. 4 inches of compacted gravel stops the slab cracking from soft spots and gives drainage. It is the cheapest insurance in the whole project.
The table lists both. This pour is 4.15 m³ with extra included — past roughly 1 yd³, a truck wins on cost and on finishing time before the concrete sets.
A single layer of welded wire mesh (or #3/#4 rebar on an 18–24 in grid) held at mid-slab on chairs. Fibre mesh in the mix is a supplement, not a substitute, at these sizes.
The headline result on this page — the complete, computed materials list for this project — is the number to plan and order with. Work down the table line by line when you order: the list already counts the easy-to-forget items, so buy each line as printed rather than estimating from the headline item alone, and round each line up to your supplier's full packs, bags or lengths.